Good Shepherd Lutheran Church

Building Update


May 2008

 

 

Day-By-Day Updates (scroll down for more photos and the Building Committee's monthly update)

Sunday, May 4, 2008: We toured our new construction site to get a feel of the space of our future facility. There is still much work to be completed before we can worship in our new space.

Friday, May 16, 2008: In spite of the rain this month has brought, construction progress continues. Most notable is progress on the office space of the second floor. The exterior walls are shaping up nicely.

May Building Committee Update:  Building Bandwagon III

Today (Sunday, May 4) as part of the church council forum, you will have the opportunity to venture on the other side of the construction fence and experience firsthand our emerging new facilities. Of course, I hope for good weather (our building is not closed up yet), but most of all I hope you experience the joy and anticipation that have filled me every time I have gone into our new facilities. If you are skeptical about our building program and not sure you want to jump on the “Building Bandwagon”, I particularly invite you to stand in the middle of our new sanctuary, look up at the exposed wooden ceiling, and imagine colorful stained glass in the 18 window openings. Then turn your attention to the chancel area and allow your mind’s eyes to see a platform with an altar table, ambo, choir, organ console, piano, instruments, and bells and a back wall with a large stained glass shepherd window in the center and exposed organ pipes on each side. Other things that you will see: the large unfinished basement (future program space), the lobby/narthex, the kitchen area, the elevator shaft, maybe even go up the stairs to see the floor of the administration area. There is much progress to report for April and more is scheduled for May.

April Progress
• Sanctuary concrete block walls - completed.
• Sanctuary roof – electrical conduit, wires and boxes installed; roof insulation begun
• 2nd level administrative area - precast planking installed and topped with layer of concrete
• Basement - duct work completed.
• Stair wells – most of concrete block completed; one stair completed.
• Chancel platform – framing completed.

May Schedule
• Sanctuary roof – to be completed.
• Chancel platform – concrete to be poured.
• 2nd level administrative area – masonry walls to be completed.
• Roof over lobby and 2nd level – joists & decking to be installed.
• Retaining walls for patio and lower level entrance – footings to be poured.

For May the front row seats of the Building Bandwagon are reserved for:
• Vicki Schmidt, our business manager, for keeping track of the building finances and paying the bills.
• The TCS on-site leadership team: Chuck Miller, VP for Field Operations, and Dave Lackey, On-site Superintendent. The efforts and responsiveness of these two gentlemen is greatly appreciated.
• Our picture taking crew: Carolyn Miller, Donna Young-Ritter, Warren Simonsen, Pastor Dave, and other unknown camera bugs. Thanks for creating a pictorial record of the construction of our new ministry facilities.
• Peter Schmidt who sang a solo in our new sanctuary, demonstrating the excellent acoustics.

Ernie Kessler – Building Committee Chair

Future Main Entrance

Altar construction continues

Office space taking shape.

 

 

 

 

 

 

 

 

 

 

 

 

 


 

 